The Court held that a clause providing that a difference was not a dispute capable of reference to adjudication until mediation had taken place did not comply with Section 108 because a party has a right to adjudicate disputes (including differences) at any time. Such a clause attempts to postpone the right to adjudicate.
HHJ Thornton QC, Technology & Construction Court
21 June 2000
C entered into a sub-contract with EN, incorporating the standard terms of sub-contract DOM/1. These contained an adjudication clause, clause 38A. A dispute arose concerning the appropriate method for valuing the work, which EN referred to adjudication.
An adjudicator was appointed by the RICS, but C applied to the Court for an injunction to stop the adjudication proceeding, relying upon 3 different arguments to say that the adjudicator had no jurisdiction.
Firstly, C said EN was obliged to identify all of the documentation comprising the sub-contract before the right to adjudicate arose, which EN had not done. The Court found that as the parties had agreed that there was a contract, to which the Act applied, and which incorporated the DOM/1 standard conditions, it was unnecessary for the Court to investigate further. EN did not have to state which documentation formed part of the contract as a pre-condition to adjudication. Indeed, that could be a dispute under the contract, although the Court did not wish to comment further on this.
The sub-contract provided for Geoff Brewer to be the named adjudicator. C said that this was a contractually binding agreement, and therefore the adjudicator appointed by the RICS had no jurisdiction. The clause naming Brewer referred to clause numberings from the previous version of DOM/1, providing for contractual adjudication on matters of set-off. C said there was a clear intention that the clause was intended to be an amendment to DOM/1 1998. The Court found there was a potential conflict: it could be thought that the parties were intending to add on an additional tier of adjudication for set-off disputes analogous with the 1980 DOM/1 conditions. Since there was confusion, the Court applied the contra proferentem rule, and construed the agreement against C who had drafted it.
The sub-contract also contained a bespoke clause stating that until a difference had been mediated, it could not be a dispute capable of being referred to adjudication (similar to clauses in ICE and NEC). No mediation had taken place, so C said there was not yet a right to adjudicate, and the adjudication was premature. The Court found that this approach conflicted with Section 108 of the Act, which provides that a party has a right to refer a dispute to adjudication at any time, and states that a dispute includes any difference. The Court viewed the clause as an attempt to postpone the right to adjudication.
Therefore, C's application for an injunction was refused.
The Court held that a clause providing that a difference was not a dispute capable of reference to adjudication until mediation had taken place did not comply with Section 108 because a party has a right to adjudicate disputes (including differences) at any time. Such a clause attempts to postpone the right to adjudicate.
Social Media cookies collect information about you sharing information from our website via social media tools, or analytics to understand your browsing between social media tools or our Social Media campaigns and our own websites. We do this to optimise the mix of channels to provide you with our content. Details concerning the tools in use are in our Privacy Notice.